    Work In Progress

    FORMWORK, REINFORCING STEEL AND INSTALLATIONS OF THE BLOCK A THIRD FLOOR SLAB + INTERIOR BRICK WALL AND DOOR COUNTERFRAMES ON THE SECOND FLOOR OF THE BLOCK B

    by ga· June 15, 2018· in WIP· 0 comments
    15.06.2018    
    Read More

    FORMWORK OF THE BLOCK A THIRD FLOOR SLAB + INTERIOR BRICK WALL AND DOOR COUNTERFRAMES ON THE SECOND FLOOR OF THE BLOCK B

    by ga· June 08, 2018· in WIP· 0 comments
    08.06.2018    
    Read More

    INTERIOR BRICK WALL AND DOOR COUNTERFRAMES ON THE SECOND FLOOR OF THE BLOCK B + LOAD-BEARING BRICK WALL AND CONCRETE OF THE BLOCK A SECOND FLOOR VERTICAL STRUCTURES

    by ga· June 01, 2018· in WIP· 0 comments
    01.06.2018  
    Read More

    INTERIOR BRICK WALL AND DOOR COUNTERFRAMES ON THE GROUND FLOOR OF THE BLOCK B + LOAD-BEARING BRICK WALL AND CONCRETE OF THE BLOCK A SECOND FLOOR VERTICAL STRUCTURES

    by ga· May 25, 2018· in WIP· 0 comments
    25.05.2018  
    Read More

    FORMWORK AND REINFORCING STEEL OF THE BLOCK A SECOND FLOOR VERTICAL STRUCTURES + INTERIOR BRICK WALLS ON THE GROUND FLOOR OF THE BLOCK B

    by ga· May 18, 2018· in WIP· 0 comments
    18.05.2018  
    Read More